September/October 2026: Capital Projects Digest

Member for

1 year 7 months
Nov 17, 2026
Boviet Substation

Boviet Substation


Electric

  • 115kV Transmission Structure Replacement
    In September, the Board of Commissioners approved bids for 30 steel poles that will  replace wooden transmission poles from the Eastern Bypass substation to the Pitt County Fairgrounds. This will harden the transmission system and increase electric reliability. The expected pole delivery date is April of 2027.
  • Distribution Substation Transformer Replacements & Point of Delivery
    Bids for two new distribution station transformers are slated to be released in November. A new transformer was delivered in July with installation anticipated by the end of this year. These units are replacing older transformers that have reached the end of their 50-year design life. By 2030, another seven distribution substation transformers will have reached their design life. One 120 MVA Point of Delivery transformer has reached the end of its useful life and is being replaced. A bid will be released in November, beginning the replacement project. Another 120 MVA Point of Delivery has been decommissioned and disposed of, along with the anticipated replacement for that one being delivered in January 2027.
  • Point of Delivery to Simpson Transmission Loop & Hudson’s Substation
    GUC crews are continuing to work on wire transfers and removals on the transmission loop project in the Simpson area. Easement acquisition, design, and tree removals are entirely complete, and contractor pole installations are complete for phase I of this project. Poles for phase II of this project are currently out for bid. The new Hudson’s Substation, designed to meet future energy demands in the growing service area, is progressing as well. Hudson Substation’s foundations are complete. The transformer, fencing and control house have also been installed.
  • Boviet Substation
    Greenville Utilities’ work to provide for Boviet Solar’s large energy need is moving forward with the construction of a 60 MVA 115kV to 12.47kV substation housing three 20MVA transformers. Two 20 MVA transformers were delivered in May and have been set. Contractors are erecting steel and installing bus. Boviet is slated to be energized by the end of December.

Facilities

  • Admin HVAC Upgrade
    The Administration HVAC Upgrade project is slated to be complete by March of 2027. The second and third floors at the Main Office continue to undergo construction. Ceiling installation has begun. This project is a renovation of the HVAC system which has reached the end of service life. Two 32-ton HVAC units are now installed on the rooftop.
  • Operations Renovation
    Work on the Engineering and Operations Building (EO) is in final contract negotiations and construction will begin shortly afterward. Updates to the Engineering and Operations Building (EO) at the Operations Center will include relocating the training room to the EO Building and adding a fitness space. The break room within Systems Support will be enlarged and there will be increased work and storage areas for Facilities.

Gas

  • Allen Road Widening
    Work on relocating gas mains along Allen Road (to accommodate the road widening project) is about 60% complete. Work has been stopped for NCDOT to complete some drainage work at the site. GUC’s contractor is expected to resume the relocation work in the Spring.
  • High Pressure Gas Facilities
    The final portion of work connecting the Old Tar Road Gate Station to Worthington Road with an 8” distribution line is almost ready to start. Construction is expected to be completed in January 2027.
  • System Integrity
    Planning is underway to replace two existing casings and pipes under railroad crossings at Greenville Boulevard and 14th Street. Work is not expected to begin until spring 2027.