Water Tower Facelift

Water Tower Facelift

October 28, 2024

The Eastside Water Tower (at Greenville Boulevard and 14th Street) has a fresh look! The recoating process is about more than just looks, though. It helps extend the life of the tank, which holds approximately 1 million gallons of treated water. 

Every two years, an inspector measures the paint thickness of GUC’s two elevated water towers to determine if recoating is needed. The last time this water tower was recoated was in 2009, and the most recent analysis of the interior and exterior of the tank revealed that a fresh coating was needed to protect it. 

The recoat process involves a pressure wash cleaning with spot sandblasting as needed. Then both the inside and outside of the tank are repainted. Finally, our GUC logo was painted on by hand. 

While the process was underway, the tower was covered in a shroud to prevent the wind from getting paint on nearby cars and buildings. The entire process took eight weeks.